Review AquaBox underground modular water storage for US projects. Define usable volume, site, equipment and procurement interfaces and request a quote.
Follow the project duty from site evidence to product review. Detention, infiltration and water reuse require different inputs.
AquaBox is a tank assembled from injection-moulded polymer elements for collecting and storing water below ground. Storage can be connected to treatment or pumping equipment when specified.
Prepare a US AquaBox request with the water duty, usable operating volume, delivery destination and design interfaces clearly identified. Use the US project resources to organize installation and procurement questions around the engineer's site design.
The catalogue illustrates tank sectors, side walls, covers and access necks, with horizontal and vertical arrangements. Inlets and outlets connect the tank to the water system. Internal mounting elements can support the equipment selected for the project.
The source catalogue describes tank sectors, covers, side walls, access necks and pipe-connection units. Mounting plates, partitions, ladders, treatment elements and pumping equipment depend on the selected arrangement. The quotation must identify what is included, optional or supplied by others.
Choose materials and equipment for the water being stored and its intended use. Potable use requires applicable evidence for the complete configuration and local requirements; it is not established by this overview. Loads, burial, watertightness and service life require configuration-specific evidence.
Coordinate the base, groundwater and uplift, connections and access with the responsible designers. The catalogue illustrates anchoring and internal equipment mounting, but does not replace project installation instructions. Keep inspection and equipment access available; agree cleaning and maintenance for the stored water and installed equipment.
Tank rings are assembled from modular half-ring elements and joined with bolted connections. The source describes a gasket or sealant at the joints and anchoring to a prepared base. These interfaces must follow the selected arrangement and project installation documents; the overview does not establish a universal foundation or burial limit.
State the project location, intended water duty and whether the request concerns reuse storage, detention, or equipment-connected operating storage. Include the engineer's required usable volume and identify the units used in survey, storage and connection information. Record the adopted design basis and the documents needed for the current procurement stage. Treat the product scope, site design, equipment interfaces and authority submissions as explicit responsibilities.
Provide grading, utilities, ground and groundwater information, surface loading and construction access. Name the engineer and asset owner, and ask which configuration instructions and interface drawings are required before procurement. State the delivery destination and separate transport, civil works, pumps, controls and commissioning from product supply. Use the US installation and maintenance resources to organize questions for the team; they do not establish product approval.
These product information packs describe construction, functions, interfaces and source reference data. They are not certificates or approved installation instructions.
How it works · Technical information · Supply and interfaces · Installation and maintenance
Reference examples from the source catalogue; confirm the selected configuration before design or purchase.
| Catalogue volume (m³) | Body length (m) | Empty tank mass (kg) |
|---|---|---|
| 20 | 5 | 1180 |
| 40 | 10 | 2180 |
| 60 | 16 | 3180 |
| 80 | 21 | 4180 |
| 90 | 23 | 4680 |
| 120 | 31 | 6180 |
Only when it is explicitly listed in the quotation. Storage, treatment and pumping have separate equipment duties and interfaces.
Potability is not established by the product name or this information pack. Confirm materials, the complete configuration, water quality and applicable local requirements before specifying potable use.
The selected configuration and quotation define the tank elements, connections, access and any internal equipment. Ask for an itemised scope and exclusions.
Yes. Send your location, intended use and available drawings or volume information; mark unknown values as unknown.
Blank project brief, revision 2026-10-07. Record values, units, sources and open items; this worksheet contains no product specifications.
Download the editable project-input worksheet (CSV)